Harlan Electric crews rebuilt eight miles of a 69kV, single-circuit, lattice line with a new double-circuit line, replacing the lattice and wood structures with two- and three-piece monopoles. We also handled all ground wells, direct embeds, and the concrete foundations.  

Although the line encompassed a railroad route, crossed Interstate 81, and required tight outage windows to keep customer substations energized, the project team completed the work on time and without safety incidents.