SLRP SAKR-KINZ Transmission

SLRP SAKR-KINZ

Client LS Power Grid New York
Completion Date 2020
Location Pennsylvania
Completed by Harlan Electric Company 

Harlan Electric Company (Harlan Electric) crews converted 7.36 miles of the existing, 69kV AC/DC, single-circuit transmission line from Lauschtown to South Akron into single circuit with the capacity to accommodate a double-circuit line in the future.  

To complete the project, they installed 23 custom steel poles; 53 light-duty steel poles; 21 concrete caisson foundations and associated anchor bolt cages; 130,200 feet of 556.5 KCMIL ACSR; 85,000 feet of 0.567-inch, 48 fiber OPGW; and 16 OPGW splice boxes.