South Street Substation Substation
SOUTH STREET SUBSTATION |
|
---|---|
Client | TRC Engineers LLC/National Grid |
Completion Date | Nov. 2018 |
Location | Providence, Rhode Island |
Completed by | Harlan Electric Company, Inc. and E.S. Boulos Company |
Harlan Electric and E.S. Boulos rebuilt the aging South Street Substation, creating a new control house and substation, to meet the area’s current and future electric demands and help revitalize downtown Providence.
Crews converted three 1,400-foot-long 115kV overhead line supply circuits from Franklin Square to the South Street substation to place cable circuits underground and re-route the 23 and 11.5kV underground feeder getaway facilities to the new substation. We also modified remote substation terminals and removed existing 115kV overhead line circuits and unused portions of existing 11.5 and 23kV feeder getaways and substation facilities, including the switchgear building.
Opened in 1919, the original South Street Substation was a major component of the city’s critical infrastructure for providing reliable power to the area. The facility required significant rehabilitation to support the growing region and, in part, because the equipment manufacturer no longer supported the substation’s resources.